Float (project management)

From Wikipedia, the free encyclopedia

(Redirected from Slack (project management))
Jump to: navigation, search

In project management, float or slack is the amount of time that a task in a project network can be delayed without causing a delay to:[citation needed]

  • subsequent tasks (free float)
  • project completion date (total float)

An activity that has a total float equal to zero is said to be a 'critical activity', which means that a delay in the finish time of this activity will cause the entire project to be delayed by the same amount of time.[citation needed] A critical activity typically has free float equal to zero, but an activity that has zero free float may not be on the critical path.

Consider the process of replacing a broken pane of glass in the window of your home. There are various component activities involved in the project as a whole; obtaining the glass and putty, installing the new glass, choosing the paint, obtaining a tin of paint, painting the new putty once it has set, wiping the new glass free of finger smears etc etc.

Some of these activities can run concurrently e.g. obtaining the glass, obtaining the putty, choosing the paint etc., while others are consecutive e.g. you cannot buy the new paint until you have chosen it, you cannot paint the new putty until the window is installed and the new putty has set. Delaying the acquisition of the glass is likely to delay the entire project - this activity will be on the critical path and have no float, of any sort, attached to it and hence it is a 'critical activity'. A relatively short delay in the purchase of the paint may not automatically hold up the entire project as you still have to wait some time for the new putty to dry before it can be painted anyway - there will be some 'free float' attached to the activity of purchasing the paint and hence it is not a critical activity. However a delay in choosing the paint in turn inevitably delays buying the paint which, although it may not subsequently mean any delay to the entire project, does mean that choosing the paint has no 'free float' attached to it - despite having no free float of its own the choosing of the paint is involved with a path through the network which does have 'total float'.

Image:CPMScheduleFloat.jpg

List of project management topics

Advanced Search
Included Web Search Engines


Safe Search

close

Top Matching Results

Occasionally Search.com will highlight specialized results that are based on the context of your query. Examples of specialized results include specific links to news, images, or video.

Top Matching Results may highlight information from other Search.com pages, content from the CNET Network of sites, or third party content. The listings are based purely on relevance. Search.com does not receive payment for listings in this section but our partners that provide this data may get paid for listing these products.

Sponsored Links

This section contains paid listings which have been purchased by companies that want to have their sites appear for specific search terms and related content. These listings are administered, sorted and maintained by a third party and are not endorsed by Search.com.

Search Results

Search.com sends your search query to several search engines at one time and integrates the results into one list which has been sorted by relevance using Search.com's proprietary algorithm. You can customize the list of search engines included in your metasearch from the preferences.

The search engines that are used in your metasearch may allow companies to pay to have their Web sites included within the results. To view the Paid Inclusion policy for a specific search engine, please visit their Web site. Search.com does not accept payment or share revenue with any search engine partner for listings in this section.